What does void turnaround time mean?
A void is generally a landlord-owned home without a tenant. In everyday use, ‘turnaround time’ can mean the time taken for works alone, or the full period between one tenancy ending and the next beginning. These are different measures. The Scottish Housing Regulator’s Charter technical guidance, for its Scottish reporting indicator, defines re-let time in calendar days from the end of the previous tenancy or repossession to the start of the new tenancy. It calculates an average using properties re-let and the calendar days they were empty, with specified exclusions. This is a useful example of a defined measure, not a universal UK rule. [2]
Measure the whole process, not just repairs
For operational reporting, state the precise start and finish points, the unit (calendar or working days), the property types counted and any exclusions. A works-only clock may start when a contractor receives access or work begins; an end-to-end clock can also include tenancy end, key return, inspection, specification, approvals, compliance checks, advertising, allocation, viewing and sign-up. Oxford City Council explicitly distinguishes contractor works targets from end-to-end relet performance and lists separate indicators for standard and major voids, contractor time and void-to-advertising time. Its published targets are that council’s local policy—not an industry-wide deadline. [3]
- Track total elapsed time alongside stage-by-stage durations.
- Record hold-ups and reasons consistently, including access, decisions, materials, complex repairs or allocation.
- Report average performance with context: property mix and a small number of major works can change the result.
Why times vary—and what clear standards improve
Turnaround depends on the home’s condition and the scale of work, but also on how promptly people coordinate inspections, decisions, contractors and lettings. Safety or structural concerns, specialist checks, unavailable materials, access issues and the time needed to match a home to a suitable applicant may all extend the end-to-end period. A short repairs target alone will not explain the whole journey.
The Chartered Institute of Housing recommends clear, realistic targets and re-let standards, defined stages, shared performance information, clear responsibilities and regular monitoring. It also recognises that void management involves balancing speed with other objectives, including a suitable letting and value for money. Clear service standards make it easier to set expectations, spot bottlenecks, escalate slippage and assess quality as well as speed. [1]
- Agree definitions and target times for each relevant property category.
- Set out who owns each stage, what information triggers the next step and how exceptions are recorded.
- Review timeliness alongside handover condition, tenant feedback, cost and reasons for delay.
Apply the measure to the work in scope
Before commissioning inspection, security assessment or clearance work, establish what the provider needs completed, who approves the scope, what access is available and how completion will be evidenced. These steps can clarify a contractor’s contribution without confusing it with the landlord’s wider re-let process. Solent Void Solutions provides property inspections, security assessments and void clearance; the appropriate scope depends on the property and the client’s requirements.